For most of the year a section of my backyard is what one would call soggy. It never used to be, since as a kid we used to grow vegetables there, but lately boots are recommended to walk around that area. I have to keep a ditch open so melt and rain water can at least partially flow away.
April 8 and the last of the snow is melting. |
The location of the new shed/garage/workshop was partially chosen because it tends to be a little dryer, and the ground firmer. This is another reason the concrete was put above ground with a single pour, and not dug down for footings, etc. While waiting for the far back conditions to improve, I was instructed to build a fence in the near back to keep the dogs in. We had recently acquired a 14 yo Shih Tzu mix from family who could no longer have a dog, to go along with our 6 yo American Eskimo Dog mix, and the two leashes setup wasn't working.
Lucy and Katie happy to be free of their leashes. |
After about 3 weeks, with the new fence completed, and the dogs able to run freely around, efforts went back on the shed. Supplies were delivered, and work began on building the walls. A pneumatic framing nailer helped speed that along, but it is still slow going working by yourself most of the time.
June 8: 2"x4"x8' and 4'x8' sheets of aspenite (OSB) |
2 walls up and two just about ready to be lifted. |
July 17: All 4 walls up. |
The opening cut for the doors |
It was now after the middle of July, and there was still a lot of work to be done. Next on the list is the trusses.
The Entire Story To Date:
The New Shed - Phase 9
The New Shed - Phase 8
The New Shed - Phase 7
The New Shed - Phase 6
The New Shed - Phase 5
The New Shed - Phase 4
The New Shed - Phase 3
The New Shed - Phase 2
The New Shed - Phase 1
No comments:
Post a Comment